In this post, we will learn about the Aluminium Formwork Worksite Management process.
Contents
Aluminium Formwork Worksite Management
Logistic
- STACKING AND STORAGE OF MATERIALS
- Design and Construction Of Pile Foundations
- Evolution of Retaining Structures
- Glossary Relating To Bitumen And Tar
- Aluminium Formwork Refurbishment
- Safety For Hydraulic Tensioning Jacks
- Methodology of Post Tensioning Work
- Properties of Prestressing HT Strand
- Losses in Pre Stress due to Elastic Shortening
- Jack Pressure for Single and Multi Pull Stressing
- Elongation & Modified Elongation in Prestressing
- Prestressing Materials Management at Site
- Prestressing : Definitions | Advantage | Application
- Slipform – Slipform Planning at Site
- Labour Productivity Norms in Slipform
- Dismantling Procedure of Slipform
- Slipform Reinforcement Schedule Planning
- Assembly of Stair Tower for Slipform
- Assembling Procedure of Tapering Slipform
- Assembling Procedure of Straight Slipform
- Classification Of Slip Form Work
- Design Considerations of SlipForm
- Evolution of Slip Form Now a Days
- Measure Horizontal Distance Using AutoLevel
- Bulking OF Fine Aggregates
- Concrete Cube Samples Taken for Different Volume
- Grades of Concrete as per IS 456 : 2000
- Flowchart For Aluform Work At Site
- Dismantling Process of Aluminium Formwork
- Assembling Process of Aluminium Formwork
- Dismantling Of Slab Aluminium Formwork
- Dismantling Of Wall Column & Beam Formwork
- Aluminium Formwork Concreting Process
- Assembling of Wall Aluminium Formworks
- Assembly Process of Aluminium Formwork
- Aluminium Formwork Worksite Management
- What is 1.54 in Concrete
- De Shuttering Period as per IS 456
- Grade Of Concrete And Its Cement, Sand And Aggregate Ratio
- Derivation Of (d²/162) – Unit Weight Of Bar
- Volume Of Different Shapes
Manpower
1. BSCC – HQ shall provide the estimated manpower requirement for the project based on the number of formwork panels to be supplied to achieve the required cycle time. This manpower requirement shall vary according to the size of formwork used on the building.2. However, the manpower requirement for other supplementary trades which complement the formwork installation such as Mechanical & Electrical (M&E) services and rebar works need to be taken into consideration also.
3. A joint effort of all operations from formwork installer, rebar, plumbing, electrical and concreting workers need to be synchronized to achieve the required cycle time.
4. Segregation and systematically allocation of duties for each formwork team are required in ensuring the optimization of productivity. Hence, each team shall be delegated or assigned to do specific jobs task on a daily basis to resemble a manufacturing production line. However, due consideration should be used in determining the level of experience and compatibility of persons when allocating tasks to minimize the risks.
Safety
1. Control measures should be taken to identify and minimize the hazards associated with work involving the assembly and dismantling of formwork equipment such as falls from height, slips, falling objects, noise, dust and manual tasks.
2. The external working brackets/platforms or scaffoldings should not be used to stack materials or equipment. This will lead to the persons working on it exposed to additional hazards in relation to trips and slips or collapse of the external working brackets/platforms or scaffolding.
3. Minimize the working heights for persons performing the assembly and dismantling formwork.
4. Mixing of formwork components should be avoided to prevent unsafe installation such as mixing pins and braces which may lead to the collapse of the formwork.
Click For Civil Engineering Videos
5. Do not allow drop stripping of formwork as it is an unsafe practice.
6. Partially assembled or dismantled formwork should be secured during break time to prevent against overturning or collapsing due to strong wind or accidentally / unintentionally knock over by workers.
7. Electrical safety should be implemented for the safe use of electrical equipment.
8. Protruding flatties or projecting nails should be removed immediately with appropriate tools at the dismantling stage.
9. Use of personal protective equipment by all persons working at work areas (such as safety harness, safety helmets, eye protection etc) should be strictly implemented.
Accessories & Tools
1. Accessories (10%) extra will be supplied for the assembly and dismantling of the formwork panels.
2. Sufficient tools required for assembling and dismantling will also be supplied as per the attached list.