In this post, we will Learn about the Assembling Procedure of Tapering Slipform at the site.

Assembling Procedure of Tapering Slipform

1. Position the vertical and horizontal reinforcement with the correct cover.
2. Casting the starter. (Provide pocket or pipe sleeve in yoke locations to accommodate tapered sleeves )
3. Check starter for the correctness in inclination level and diameter. Chip and finish the same, if required.
4. Erect central tower using L&T HDT system and fix planks on the top after aligning the top construction accurately.
5. Fix the centre frames with the help of scaffold pipes, if required.
6. Pre-assemble the trusses and spiders after marking the location of inside yoke leg, assemble with yoke legs, yoke beams, adjusting screws as per initial setting diagram, erect them and provide support.
7. Check the level of truss.
8. Mark the position of inside and outside yokes in the starter starting from the tower location.
9. Assemble the panels along with form supports with pre-assembled condition.
10. Fix top and bottom waler. Fix external supports both horizontal and inclined to align the shutter.
11. Fix inside and outside consoles and upper outside console and fix planks.
12. Fix the yoke beams at top & bottom.
13. Check the level of yoke beams with spirit levels.
14. Fix the top platform pipes with guard railings.
15. Fix the jacks & turnbuckle jacks and finish the hydraulic connections.
16. Test for leakage in the line and jacks and replace, if required.
17. Fix water level tubes & check the platform level. Adjust if required.
18. Check the final adjustment as per the initial setting diagram.
19. Fix the handrails.
20. Fix the tapered sleeves & jack rods.
21. Energise the slipform before filling the form and removing temporary supports.
22. Start the concreting after completion of all activities and checking the availability of all materials as given in the planning for slipform.
23. Fix the inside and outside hanging scaffold and do the decking.

24. Tie the safety net.

I hope you find this information useful. If there is something that I have missed or I do not know, you can comment and tell me which I will try to rectify as soon as possible.
If you have liked this post of mine, then use the social link given below and share it among your friends on social media. Thanks