In this post, I am going to explain to you the De Shuttering Period as per IS 456

De Shuttering Period as per IS 456

Forms shall not be released until the concrete has achieved a strength of at least twice the stress to which the concrete may be subjected at the time of removal of formwork.

The strength referred to shall be that of concrete using the same Cement, Aggregate and admixture. If any, with the same proportions and cured under conditions of temperature and moisture similar to those existing on the work.

While the above criteria of strength shall be the guiding factor for removal of formwork. In normal circumstances where ambient temperature does not fall below 15 degrees, Celcius and where Ordinary Portland Cement is used and adequate curing are done, Following stripping period may deem to satisfy the guideline given below.

the De Shuttering Period as per IS 456
For other cement and lower temperature, the stripping time recommended above may be suitably modified.
If You Want Detailed Knowledge Then Watch My Video On YouTube Channel: Civil Learning Technology.  I Am Telling This Because Many Important Points I Have Covered During Making Of Video, So If You Want To Know In Detail Then Watch My Video On YouTube Which is Given Below.
I hope you find this information useful. If there is something that I have missed or I do not know, you can comment and tell me which I will try to rectify as soon as possible.
If you have liked this post of mine, then use the social link given below and share it among your friends on social media. Thanks
SHARE THIS POST, IF YOU LIKE IT !!
Padhega India Tab Hi Badhega India | पढ़ेगा इंडिया तब ही बढ़ेगा इंडिया

2 thoughts on “De Shuttering Period as per IS 456”

Leave a Comment