In this post, we are going to learn about the Assembly Process of Aluminium Formwork at the site.
Assembly Process of Aluminium Formwork
Setting Up Level & Marking Of Position
The project surveyor shall mark based on the approved construction drawings to ensure that the grid line and level of the foundation level are properly set up, marked for walls, columns etc. Levelling must be checked prior to commencement of formwork installation to ensure accurate positioning.
Formwork Panels
1. Cleaning of the surface and side panel of the formwork after each usage shall be done immediately using proper tools.
2. Ensure that all front and side panel of formwork is properly coated with a recommended Form release agent that prevents from sticking and concrete build-up aluminium form surfaces. It protects and prolongs the useful lives of the aluminium formwork.
3. The following precautions shall be taken when applying the Form oil on the aluminium panels
(a) The best results are obtained when a uniform application of Form oil is applied immediately following stripping and subsequent cleaning of the panels. Always ensure that the coated form surfaces are allowed to dry prior to placing concrete.
- STACKING AND STORAGE OF MATERIALS
- Design and Construction Of Pile Foundations
- Evolution of Retaining Structures
- Glossary Relating To Bitumen And Tar
- Aluminium Formwork Refurbishment
- Safety For Hydraulic Tensioning Jacks
- Methodology of Post Tensioning Work
- Properties of Prestressing HT Strand
- Losses in Pre Stress due to Elastic Shortening
- Jack Pressure for Single and Multi Pull Stressing
- Elongation & Modified Elongation in Prestressing
- Prestressing Materials Management at Site
- Prestressing : Definitions | Advantage | Application
- Slipform – Slipform Planning at Site
- Labour Productivity Norms in Slipform
- Dismantling Procedure of Slipform
- Slipform Reinforcement Schedule Planning
- Assembly of Stair Tower for Slipform
- Assembling Procedure of Tapering Slipform
- Assembling Procedure of Straight Slipform
- Classification Of Slip Form Work
- Design Considerations of SlipForm
- Evolution of Slip Form Now a Days
- Measure Horizontal Distance Using AutoLevel
- Bulking OF Fine Aggregates
- Concrete Cube Samples Taken for Different Volume
- Grades of Concrete as per IS 456 : 2000
- Flowchart For Aluform Work At Site
- Dismantling Process of Aluminium Formwork
- Assembling Process of Aluminium Formwork
- Dismantling Of Slab Aluminium Formwork
- Dismantling Of Wall Column & Beam Formwork
- Aluminium Formwork Concreting Process
- Assembling of Wall Aluminium Formworks
- Assembly Process of Aluminium Formwork
- Aluminium Formwork Worksite Management
- What is 1.54 in Concrete
- De Shuttering Period as per IS 456
- Grade Of Concrete And Its Cement, Sand And Aggregate Ratio
- Derivation Of (d²/162) – Unit Weight Of Bar
- Volume Of Different Shapes
(b) Do not over apply. Excess Form oil can adversely affect performance and should be picked up promptly with rags.
(c) Prevent Form oil overspray from contacting reinforcing Steel bars and/ or tensioning cables.
I hope you find this information useful. If there is something that I have missed or I do not know, you can comment and tell me which I will try to rectify as soon as possible.
If you have liked this post of mine, then use the social link given below and share it among your friends on social media. Thanks