In this post, we will learn about the Dismantling Procedure of Slipform at site practically.
Dismantling Procedure of Slipform
Straight Slipform
1. Provide coil nuts in the final layer of concrete approximately 300 mm from top of concrete.
2. Fix dismantling brackets, handrails, finish planking and transfer a load of slipform assembly to the brackets.
3. Remove the flying tie rod assembly and lower the same.
4. Remove the inside and outside hanging scaffold and shift the planks to the staging brackets.
5. Remove the jacks and sleeves.
6. Remove the yoke assembly, which consists of yoke legs, yoke beams and waler shoes.
7. Remove inside & outside walers.
8. Remove the wall forms, while removing the water.
9. Extract the jack rods and grout the holes.
10. Remove dismantling brackets after completing other works.
- STACKING AND STORAGE OF MATERIALS
- Design and Construction Of Pile Foundations
- Evolution of Retaining Structures
- Glossary Relating To Bitumen And Tar
- Aluminium Formwork Refurbishment
- Safety For Hydraulic Tensioning Jacks
- Methodology of Post Tensioning Work
- Properties of Prestressing HT Strand
- Losses in Pre Stress due to Elastic Shortening
- Jack Pressure for Single and Multi Pull Stressing
- Elongation & Modified Elongation in Prestressing
- Prestressing Materials Management at Site
- Prestressing : Definitions | Advantage | Application
- Slipform – Slipform Planning at Site
- Labour Productivity Norms in Slipform
- Dismantling Procedure of Slipform
- Slipform Reinforcement Schedule Planning
- Assembly of Stair Tower for Slipform
- Assembling Procedure of Tapering Slipform
- Assembling Procedure of Straight Slipform
- Classification Of Slip Form Work
- Design Considerations of SlipForm
- Evolution of Slip Form Now a Days
- Measure Horizontal Distance Using AutoLevel
- Bulking OF Fine Aggregates
- Concrete Cube Samples Taken for Different Volume
- Grades of Concrete as per IS 456 : 2000
- Flowchart For Aluform Work At Site
- Dismantling Process of Aluminium Formwork
- Assembling Process of Aluminium Formwork
- Dismantling Of Slab Aluminium Formwork
- Dismantling Of Wall Column & Beam Formwork
- Aluminium Formwork Concreting Process
- Assembling of Wall Aluminium Formworks
- Assembly Process of Aluminium Formwork
- Aluminium Formwork Worksite Management
- What is 1.54 in Concrete
- De Shuttering Period as per IS 456
- Grade Of Concrete And Its Cement, Sand And Aggregate Ratio
- Derivation Of (d²/162) – Unit Weight Of Bar
- Volume Of Different Shapes
Tapering Slipform
1. Provide coil nuts in the final layer of concrete.
2. Fix dismantling brackets, handrails, and fix the planks.
3. Remove and re-locate the R.G.Hoist to the required location (if it is there).
4. Transfer the load of slipform assembly and main truss to the wall.
5. Remove & re-fix the safety net with the temporary platform.
6. Remove the inside & outside hanging scaffolding.
7. Remove all the hydraulic hoses, manifolds and the jacks.
8. Remove the intermediate form supports, spindles, turnbuckle, shutters, form supports, wall thickness screws, radius screws and yoke beams.
9. Remove inside & outside yoke legs.
10. Dismantle the truss assembly.
11. Extract the jack rods and grout the hole.
12. Lower the materials then and there.
13. Remove the dismantling platform.
I hope you find this information useful. If there is something that I have missed or I do not know, you can comment and tell me which I will try to rectify as soon as possible.
If you have liked this post of mine, then use the social link given below and share it among your friends on social media. Thanks
SHARE THIS POST, IF YOU LIKE IT !!
Padhega India Tab Hi Badhega India | पढ़ेगा इंडिया तब ही बढ़ेगा इंडिया