In this post, we will learn about the Flowchart For Aluform Work At Site.

Flowchart For Aluform Work At Site

Flowchart For Aluform Work At Site

ACTIVITY FOR THE FLOW CHART NUMBERS

1. Receive Aluform materials.
1a. Packing list, BOQ, and Formwork layout.
1b. Tools.
1c. Additional accessories.

2. Visual inspection.
2a. Packing list & schemes.
2b. Acceptance criteria.

3. Inform concern for any defects.
3a. Details of the report.

4. Collect modification details.
4a. Fabrication drawings.

5. Stock the material as per packing list.

6. Room wise segregation.

7. Dry mock-up.
7a. Schemes.

8. Room wise numbering for identification.

9. Dismantling of mock-up.

10. Setting out.

11. Shift to the work location.

12. Shift to the stockyard.

13. Actual assembly at work location.

14. Slab rebars & M&E works.

15. Final checking (Pre pour check)
15a. Checklist.

16. Concreting.
16a. Pour card.

17. Post pour check.

18. Levelling and finishing.

19. De-shuttering.
19a. Removing pins and wedges.
19b. Removing wall ties.
19c. Removal of wall panels.
19d. removal of deck panels.

20. Cleaning of panels.

21. Fixing of working platforms with brackets.

22. Erection of safety posts/rails.

23. Applying form release agent.

I hope you find this information useful. If there is something that I have missed or I do not know, you can comment and tell me which I will try to rectify as soon as possible.
If you have liked this post of mine, then use the social link given below and share it among your friends on social media. Thanks
SHARE THIS POST, IF YOU LIKE IT !!
Padhega India Tab Hi Badhega India | पढ़ेगा इंडिया तब ही बढ़ेगा इंडिया

2 thoughts on “Flowchart For Aluform Work At Site”

Leave a Comment