In this post, we will learn about Summary of Labour Productivity Norms in Slipform work at the site.
Labour Productivity Norms in Slipform
SL NO.
|
TYPES OF WORK
|
UNIT
|
NORMS IN M/Hours
|
1
|
Erection of Access Tower (2.5 X 2.5 M)
|
RM
|
32
|
2
|
Dismantling of Access Tower (2.5 X 2.5 M)
|
RM
|
15
|
3
|
Erection of Stair Tower (2.5 X 2.5 M)
|
RM
|
16
|
4
|
Dismantling of Stair Tower (2.5 X 2.5 M)
|
RM
|
8
|
5
|
Straight Slipform Assembly
|
YOKE SET
|
75
|
6
|
Straight Slipform Dismantling
|
YOKE SET
|
55
|
7
|
Slipform Operation – Straight Slipform
|
M2
|
1.22
|
8
|
Assembly of Pre-Stressed Silo
|
YOKE SET
|
92
|
9
|
Slipform Concrete – Manual
|
M3
|
22
|
10
|
Slipform Concrete – Rmc With Pump
|
M3
|
15
|
11
|
Slipform Concrete – Rmc With Hoist
|
M3
|
25
|
12
|
Slipform Reinforcement – Straight Slipform
|
MT
|
65
|
13
|
Extraction of Climbing Rod
|
RM
|
0.34
|
14
|
Taper Slipform Assembly – Upto 24 Yoke Set
|
MT
|
56
|
15
|
Taper Slipform Assembly – 16 To 48 Yoke Set
|
MT
|
49
|
16
|
Taper Slipform Dismantling – Upto 24 Yoke Set
|
MT
|
49
|
17
|
Taper Slipform Dismantling – 16 to 48 Yoke Set
|
MT
|
46
|
18
|
Re-Assembly of Slipform – Taper Slipform
|
MT
|
78
|
19
|
Re-Assembly of Slipform – Straight Slipform
|
YOKE SET
|
90
|
20
|
Slipform Operation – Taper Slipform
|
M2
|
2.45
|
21
|
Slipform Reinforcement – Taper Slipform
|
MT
|
90
|
22
|
Erection of R.G.Hoist
|
NOS
|
827
|
23
|
Re-Location of R.G.Hoist
|
NOS
|
1365
|
24
|
Dismantling of R.G.Hoist
|
NOS
|
675
|
25
|
Pre-Stressing Works in Silos
|
MT
|
170
|
Note: The productivity norms will vary based on the volume of work involved and the number of structures to be constructed in the project.
- STACKING AND STORAGE OF MATERIALS
- Design and Construction Of Pile Foundations
- Evolution of Retaining Structures
- Glossary Relating To Bitumen And Tar
- Aluminium Formwork Refurbishment
- Safety For Hydraulic Tensioning Jacks
- Methodology of Post Tensioning Work
- Properties of Prestressing HT Strand
- Losses in Pre Stress due to Elastic Shortening
- Jack Pressure for Single and Multi Pull Stressing
- Elongation & Modified Elongation in Prestressing
- Prestressing Materials Management at Site
- Prestressing : Definitions | Advantage | Application
- Slipform – Slipform Planning at Site
- Labour Productivity Norms in Slipform
- Dismantling Procedure of Slipform
- Slipform Reinforcement Schedule Planning
- Assembly of Stair Tower for Slipform
- Assembling Procedure of Tapering Slipform
- Assembling Procedure of Straight Slipform
- Classification Of Slip Form Work
- Design Considerations of SlipForm
- Evolution of Slip Form Now a Days
- Measure Horizontal Distance Using AutoLevel
- Bulking OF Fine Aggregates
- Concrete Cube Samples Taken for Different Volume
- Grades of Concrete as per IS 456 : 2000
- Flowchart For Aluform Work At Site
- Dismantling Process of Aluminium Formwork
- Assembling Process of Aluminium Formwork
- Dismantling Of Slab Aluminium Formwork
- Dismantling Of Wall Column & Beam Formwork
- Aluminium Formwork Concreting Process
- Assembling of Wall Aluminium Formworks
- Assembly Process of Aluminium Formwork
- Aluminium Formwork Worksite Management
- What is 1.54 in Concrete
- De Shuttering Period as per IS 456
- Grade Of Concrete And Its Cement, Sand And Aggregate Ratio
- Derivation Of (d²/162) – Unit Weight Of Bar
- Volume Of Different Shapes
I hope you find this information useful. If there is something that I have missed or I do not know, you can comment and tell me which I will try to rectify as soon as possible.
If you have liked this post of mine, then use the social link given below and share it among your friends on social media. Thanks
SHARE THIS POST, IF YOU LIKE IT !!
Padhega India Tab Hi Badhega India | पढ़ेगा इंडिया तब ही बढ़ेगा इंडिया