In this post, we will learn about the Aluminium Formwork Concreting Process at Site.
Aluminium Formwork Concreting Process
Pre-Check Before Concreting
1. Ensure that the position of the walls and column formwork are in accordance with the set up marking.
2. Check to ensure correct spacing of props for slab formwork.
3. Check the verticality and horizontality level of the wall and slab panels respectively.
4. Ensure that all pins, wedges and ties are properly secured and tightened.
5. Re-check the opening such as door and window panels are correct.
6. Re-check all popping stands to ensure its height are in accordance to drawings.
7. Adequate bracing (if necessary) to ensure stability.
8. Ensure cover blocks are placed correctly.
- STACKING AND STORAGE OF MATERIALS
- Design and Construction Of Pile Foundations
- Evolution of Retaining Structures
- Glossary Relating To Bitumen And Tar
- Aluminium Formwork Refurbishment
- Safety For Hydraulic Tensioning Jacks
- Methodology of Post Tensioning Work
- Properties of Prestressing HT Strand
- Losses in Pre Stress due to Elastic Shortening
- Jack Pressure for Single and Multi Pull Stressing
- Elongation & Modified Elongation in Prestressing
- Prestressing Materials Management at Site
- Prestressing : Definitions | Advantage | Application
- Slipform – Slipform Planning at Site
- Labour Productivity Norms in Slipform
- Dismantling Procedure of Slipform
- Slipform Reinforcement Schedule Planning
- Assembly of Stair Tower for Slipform
- Assembling Procedure of Tapering Slipform
- Assembling Procedure of Straight Slipform
- Classification Of Slip Form Work
- Design Considerations of SlipForm
- Evolution of Slip Form Now a Days
- Measure Horizontal Distance Using AutoLevel
- Bulking OF Fine Aggregates
- Concrete Cube Samples Taken for Different Volume
- Grades of Concrete as per IS 456 : 2000
- Flowchart For Aluform Work At Site
- Dismantling Process of Aluminium Formwork
- Assembling Process of Aluminium Formwork
- Dismantling Of Slab Aluminium Formwork
- Dismantling Of Wall Column & Beam Formwork
- Aluminium Formwork Concreting Process
- Assembling of Wall Aluminium Formworks
- Assembly Process of Aluminium Formwork
- Aluminium Formwork Worksite Management
- What is 1.54 in Concrete
- De Shuttering Period as per IS 456
- Grade Of Concrete And Its Cement, Sand And Aggregate Ratio
- Derivation Of (d²/162) – Unit Weight Of Bar
- Volume Of Different Shapes
Monitoring During Concreting Process
1. Ensure site coordinators are available and on stand-by during the concreting process.
2. Always ensure that concrete pouring is disturbed evenly throughout the wall sections before commencing to cast the slab level areas. This is to prevent loading pressure on the formwork panels due to uneven casting.
3. Re-check the areas whenever cement slurry leakage is noted to determine the cause of it. Remedy work should be done immediately to ensure the concreting process is not affected.
4. During concreting, always ensure that immediate steps is taken to remove/clean all the access concrete that is stuck on the back of the formwork panels. Non-removal will result in the formwork panels getting too heavy and also the scrapping task after the concrete has dried up becomes more tedious.
I hope you find this information useful. If there is something that I have missed or I do not know, you can comment and tell me which I will try to rectify as soon as possible.
If you have liked this post of mine, then use the social link given below and share it among your friends on social media. Thanks
SHARE THIS POST, IF YOU LIKE IT !!
Padhega India Tab Hi Badhega India | पढ़ेगा इंडिया तब ही बढ़ेगा इंडिया