Today in this tutorial I am going to tell you How to calculate Cement, Sand and Aggregate Quantity in Concrete in very easy steps at Construction Sites.

Cement, Sand and Aggregate Quantity in Concrete

Here I have consider Concrete Volume (WET) = 1 Cubic Meter
 
Grade of Concrete Mix = M15 (Cement = 1 : Sand = 2 : Aggregate = 4)
 
Sum of the ratio of Cement, Sand & Aggregate = 1+2+4 = 7
 
First we have to find the Dry Volume of Concrete by Increasing the Wet Volume by 54 percent.
 
Dry Volume = Wet Volume x (54% of Wet Volume)
                       = 1 x (54  x 1 / 100) = 1.54 Cubic Meter
 
Now we have to find the quantity of Cement, Sand & Aggregate. Here I will show you the calculation of quantity in different units like Cubic Meter, KG, Bags, Cubic Feet.
 
CEMENT
 
1) Cubic Meter = Dry Volume x (Ratio of Cement / Sum of Total Ratio)
                            = 1.54 x (1 / 7) = 0.22 Cubic Meter
 
2) KG = Dry Volume x (Ratio of Cement / Sum of Total Ratio) x Density of Cement
           = 1.54 x (1 / 7) x 1440 = 316.8 KG
 
3) Bags = We know, 50 KG = 1 Bag of Cement 
                              316.8 KG = 316.8 / 50 = 6.336 Bags of Cement
 
4) Cubic Feet = If we multiply Number of Cement bags by 1.226, we get the value in Cubic Feet i.e. 6.336 x 1.226 = 7.77 Cubic Feet
 
 
SAND
 
1) Cubic Meter = Dry Volume x (Ratio of Sand / Sum of Total Ratio)
                            = 1.54 x (2 / 7) = 0.44 Cubic Meter
 
2) KG = Dry Volume x (Ratio of Sand / Sum of Total Ratio) x Density of Sand
           = 1.54 x (2 / 7) x 1450 = 638 KG
 
[Density of Sand varies between 1450 – 1500 KG per Cubic Meter]
 
3) Cubic Feet = Dry Volume x (Ratio of Sand / Sum of Total Ratio) x 35.3147
                        = 1.54 x (2 / 7) x 35.3147 = 15.54 Cubic Feet
 
[NOTE : 1 Cubic Meter = 35.3147 Cubic Feet]
 
ALTERNATIVE : No. of Cement Bags x Value of one bag of cement in Cubic Feet x Ratio of Sand
                           = 6.336 x 1.226 x 2 = 15.54 Cubic Feet
 
AGGREGATE
 
1) Cubic Meter = Dry Volume x (Ratio of Aggregate / Sum of Total Ratio)
                            = 1.54 x (4 / 7) = 0.88 Cubic Meter
 
2) KG = Dry Volume x (Ratio of Aggregate / Sum of Total Ratio) x Density of Aggregate
           = 1.54 x (4 / 7) x 1500 = 1320 KG
 
[Density of Aggregate varies between 1450 – 1550 KG per Cubic Meter]
 
3) Cubic Feet = Dry Volume x (Ratio of Aggregate / Sum of Total Ratio) x 35.3147
                        = 1.54 x (4 / 7) x 35.3147 = 31.07 Cubic Feet
 
[NOTE : 1 Cubic Meter = 35.3147 Cubic Feet]
 
ALTERNATIVE : No. of Cement Bags x Value of one bag of cement in Cubic Feet x Ratio of Aggregate
                           = 6.336 x 1.226 x 4 = 31.07 Cubic Feet
 
Below I Am Uploading My Hand Made Documents For You Only On Your Request, So That You Can Download It From Here. But One Thing Keep In Mind That This Is Only The Hand Made Notes.
 
If You Want Detailed Knowledge Then Watch My Video On YouTube Channel: Civil Learning Technology.  I Am Telling This Because Many Important Points I Have Covered During Making Of Video, So If You Want To Know In Detail Then Watch My Video On YouTube Which is Given Below.

 

 
SHARE THIS POST, IF YOU LIKE IT !!
Padhega India Tab Hi Badhega India | पढ़ेगा इंडिया तब ही बढ़ेगा इंडिया

 

3 thoughts on “Cement, Sand and Aggregate Quantity in Concrete”

Leave a Comment